Skip to content
Join our Newsletter

Georgia Power begins last series of tests on new nuclear unit

Vogtle Unit 4 is projected to enter service in late fourth quarter 2023 or first quarter 2024.
Georgia Power
Credit: Georgia Power

Georgia Power has begun hot functional testing on its Vogtle Unit 4.

Hot functional testing marks the last series of major tests underway for the new nuclear unit ahead of an initial fuel load. The testing represents a significant step towards operations. 

Hot functional testing is conducted to verify the successful operation of reactor components and systems together and confirm the reactor is ready for fuel load. 

As part of the testing, the site team will begin running unit four plant systems, without nuclear fuel in the reactor, and advance through the testing process towards reaching normal operating pressure and temperature.

As part of the testing process, nuclear operators will use the heat generated by the unit's four reactor coolant pumps to raise the temperature and pressure of plant systems to normal operating levels. 

Once normal operating temperature and pressure levels are achieved and sustained, the unit's main turbine will be raised to normal operating speed using steam from the plant. 

During these series of tests, nuclear operators will be able to exercise and validate procedures as required ahead of fuel load. 

Vogtle Unit 4 is projected to enter service in late fourth quarter 2023 or first quarter 2024.

Once operating, the two new units are expected to power more than 500,000 homes and businesses. 

Southern Nuclear will operate the new units on behalf of the co-owners: Georgia Power, Oglethorpe Power, MEAG Power and Dalton Utilities.

For more information, click here